Saturday 4 February 2017

Rampion wind farm progress


From Hove seafront
Installation of the 116 monopole foundations was completed last November. On a clear day the northernmost ones can be seen with the naked eye. Sixty interconnecting cables were also laid, followed in December by two 16km long export cables. Installation of the remaining 62 cables and the turbines is planned to start this spring.